Commercial Modular Construction for Shira Dental Clinic


SMM won a $711,135 contract for a 10,000 SF DENTAC Dental Command HQ for the Army.  Patients, Army Command personnel and Clinic Staff use this building while a local General Contractor is renovating portions of an existing Dental Clinic/HQ at Fort Polk.  The Army Corps of Engineers oversaw the project. were used throughout.

Building Features include:

  • Parapet Roof
  • 480 V HVAC’s
  • Sustainable, energy efficient materials used throughout
  • Dental Lab for Castings
  • X-Ray Equipment
  • Vacuum and Compressed Air Lines
  • (11) Two chair Dental Treatment Suites
  • (2) Endo-Operatory Rooms for Dental Surgery
  • Fire Protection (Alarms and Sprinklers)

Project Challenges

– 120 day schedule
– Multiple electrical voltages (208V & 480V)
– Site Grade complications
– Coordination of relocation and installation of the existing Dental Clinic’s Furniture and Equipment

Testimonial

"SMM completed the project properly, safely and on schedule. A job well done.” - J & J Maintenance

Floor Plans

Enlarge this floor plan »